Define the sequence before testing
An interlock is meaningful only in relation to a specific operating procedure and equipment configuration. Start by identifying the devices involved, their normal positions, the intended order of operation, and the conditions that permit each action. Depending on the design, this may include breakers, disconnecting devices, doors, transfer controls, or other mechanically or electrically interlocked components. Do not assume that two lineups with similar functions use identical logic.
Translate operating procedures into test cases with an expected result for each step. A permitted sequence should state the starting condition, required operator action, permissive conditions, and resulting device state. A prohibited sequence should identify the attempted action and the reason it must be blocked. Engineering should resolve ambiguous procedures before testing; a test cannot establish whether an undocumented sequence is acceptable.
Prove permitted and blocked actions
For each permitted sequence, verify that the required conditions are present and that the intended action can proceed in the correct order. Record the initial state, each operation, indication or control response, and final state. Where the design includes multiple control stations or operating modes, account for the applicable differences rather than assuming one test represents every configuration.
Then challenge the interlock by attempting defined prohibited actions under controlled test conditions. Confirm that the intended action is prevented and that the system does not indicate a misleading completion state. Testing should follow approved procedures, use suitable test methods, and be performed by qualified personnel. Never defeat an interlock or operate equipment in a way that exposes people to electrical or mechanical hazards merely to demonstrate a blocked sequence.
Include loss-of-power cases
Loss of control power can change what operators can command, what indications remain available, and whether an interlock holds its state. Specify which source or circuit is being interrupted, the switchgear condition at the time, and the expected behavior during the interruption and after restoration. Consider loss of normal control power, loss of a separate control supply where provided, and restoration or transfer behavior only when those conditions apply to the design.
The test plan should distinguish a device that remains mechanically restrained from one whose electrical permissive or status indication becomes unavailable. Define whether a requested operation must be blocked, whether a device must remain in its last position, and what action is required after power returns. Do not assume a spring return, fail-safe response, or automatic restoration behavior. Confirm the intended response against the approved drawings, control logic, and operating procedure.
Specify evidence and acceptance
A useful record ties every test to the applicable drawing revision, equipment identification, operating condition, expected response, observed result, and disposition of any discrepancy. Note whether the test was performed with control power applied, intentionally interrupted, or restored, and identify any simulation used. This creates a reviewable basis for engineering acceptance and helps prevent a later field team from relying on informal verbal expectations.
Agree on acceptance criteria before the test begins. Criteria should address both successful permitted operations and successful prevention of prohibited ones, including indication and recovery behavior where specified. A failed or unclear result should trigger review of wiring, logic, mechanical adjustment, or procedure as applicable; it should not be resolved by changing the expected result without engineering approval. Define who reviews exceptions and authorizes retesting.
Coordinate scope with the order
When requesting a quote for new switchgear or a custom-built configuration, share the one-line diagram, control schematics, equipment schedule, operating sequence, and applicable drawing revisions. Identify interlocked devices, required operating modes, control-power sources, intended loss-of-power scenarios, and any project-specific test documentation. State whether the scope is factory testing, field testing, or both; the parties responsible for each; and the witness or record requirements. The exact scope, availability, and timeline are confirmed for each order.
For Georgia projects, coordinate delivery timing with the site’s receiving plan, installation sequence, and readiness for qualified commissioning personnel. Nationwide shipping can be arranged for the order, but delivery does not replace site-specific engineering review or commissioning. Before shipment or handoff, align the approved test procedure, unresolved exceptions, drawings, and operating instructions so the receiving team knows which sequences were demonstrated and which conditions require verification at the installation.