New electrical distribution equipment, built around your projectServing Georgia
Gray electrical switchgear below overhead conduit in an equipment room.

Testing

Automatic Transfer Switch Commissioning

Automatic transfer switch commissioning verifies that the equipment recognizes source conditions and follows the intended transfer sequence before it supports a facility load. For Georgia engineers, contractors, and facility teams, the work should reflect the actual control settings, emergency-power design, operating procedures, and any bypass-isolation features—not a generic test script.

Made in USAUL 891 switchboard assemblies — low voltage onlyAccelerated lead times — confirm availability
Project-specific

Define the application and requirements.

Built in the USA

Discuss equipment and assembly options.

Schedule-aware

Confirm lead times for your order.

Define the sequence before testing

Start with the approved one-line diagram, transfer-switch submittal, control schematic, and sequence of operations. Confirm which sources the switch monitors, which source is normal, the designated alternate source, whether transfer is open or closed transition, and how the load is expected to behave during a source change. The commissioning plan should identify test boundaries, responsible qualified personnel, required operating permits, and who can authorize interruption or simulated conditions.

Resolve specification questions before equipment is ordered or a test date is set. Ask whether the application requires automatic, nonautomatic, or manual operation; how many switches and sources are involved; what controls or remote status points are needed; and whether bypass-isolation is specified. Share the system voltage, phase, frequency, current and withstand requirements, available fault-current information, enclosure and environmental conditions, and project drawings. Final design and ratings require engineering review and applicable authority approval.

Verify source sensing and settings

Check that voltage and frequency sensing correspond to the actual source connections and approved settings. Commissioning should confirm the programmed pickup and dropout thresholds, time delays, phase-loss or phase-sequence response where provided, and any source-available indication. Compare observed indications with instrument measurements and the control documentation; a status lamp alone does not establish that sensing is correct.

Test the sensing response using the method approved for the equipment and site, such as controlled source simulation or an authorized test procedure. Do not create an uncontrolled outage or expose personnel to energized parts. Record the conditions that initiate an unavailable-source state and the conditions required before the controller accepts a source as restored. If measured behavior differs from the approved sequence, stop and resolve wiring, settings, or source-quality questions before proceeding.

Prove transfer timing and load behavior

Exercise the transfer sequence under a documented test plan. Verify the delay before transfer, engine-start signal where applicable, source acceptance, transfer command, and any programmed in-phase or transition behavior. Measure and record elapsed times at the defined test points rather than relying on an operator’s estimate. Confirm that the sequence matches the approved settings and that connected equipment responds as intended.

Coordinate load conditions with facility operations and the generator or alternate-source team. Testing at no load may not demonstrate behavior under operating conditions, while a loaded test requires an agreed load plan and appropriate controls. Establish who monitors the load, who can abort the test, and what conditions require a return to normal service. Any change to settings or sequence should be approved, documented, and retested as needed.

Confirm retransfer and alarms

After normal source restoration, verify the source-acceptable criteria, retransfer delay, transfer back to the normal source, and any engine cooldown or stop signal. Confirm whether retransfer is automatic or requires operator action, and whether the approved sequence includes an intentional delay to avoid repeated switching during unstable restoration. Record actual timing and source conditions so facilities staff can distinguish expected operation from a fault.

Test available alarms and indications against the control drawings and monitoring-point schedule. Depending on the design, these may include source unavailable, switch position, failure to transfer, bypass position, or controller trouble. Check local annunciation and remote reporting interfaces included in the project scope, and verify that labels identify the correct source and device. Do not assume every alarm or communication point is included; reconcile the specified points with the delivered configuration.

Test bypass functions and close out

Where bypass-isolation equipment is present, use the manufacturer’s approved procedure to verify its operating positions, interlocks, indications, and permitted maintenance path. Confirm that the test does not unintentionally interrupt the load or defeat protection. Bypass operation can depend on the specific assembly and system arrangement, so commissioning personnel should follow the approved drawings and instructions rather than infer a sequence from another installation.

Closeout should capture test conditions, source and load states, measured timing, alarm results, bypass results where applicable, unresolved exceptions, approved setting changes, and retest status. Provide the final record to the owner and operations team with the current one-line, control documents, and operating instructions. For Georgia delivery planning, share the project location, receiving constraints, required configuration, submittal schedule, and commissioning milestones; shipping and availability are confirmed for each order. Before requesting a quote, send the drawings, source sequence, timing requirements, alarm list, and bypass scope so the proposed new assembly can be evaluated against the project.

Planning reference

Project specifications

Specifications are confirmed for each order
ScopeRequested by quote
VoltageBased on project requirements
CurrentSpecified to order
ListingDependent on the applicable assembly. UL 891 applies to applicable low-voltage switchboard assemblies, not medium- or high-voltage equipment.
Request a Quote