Manufacturing teams planning motor control center upgrades need to balance equipment condition with production demands. A phased approach can help define which starters and control sections must change, what interfaces must remain compatible, and when crews can work around scheduled outages. We build new switchgear and motor control equipment to an agreed project scope, with Georgia delivery coordinated to the plant schedule.

Made in USAUL 891 switchboard assemblies — low voltage onlyAccelerated lead times — confirm availability
Project-specific

Define the application and requirements.

Built in the USA

Discuss equipment and assembly options.

Schedule-aware

Confirm lead times for your order.

Build the upgrade around production phases

Start by dividing the existing motor control center work into practical outage packages. Group motors by process area, production line, or shutdown dependency, then identify which sections can be replaced together and which must remain in service. This helps engineering and operations assess the sequence, temporary operating constraints, and points where a change in one area affects another.

A phased plan also shapes the new equipment configuration. Confirm whether the project calls for a replacement lineup, additions to an existing lineup, or new sections arranged to connect with retained equipment. Record available floor space, lineup dimensions, feeder entry direction, cable access, and any limits on moving equipment through the plant. The final design and interface details require project-specific engineering review.

Collect motor and starter information

A useful starter schedule identifies each motor’s nameplate voltage, horsepower, full-load current, service factor when applicable, and driven load. Include starting method, overload requirements, operating duty, and any known acceleration or load characteristics. For variable-frequency drives or soft starters, document the device type and relevant input, output, and bypass arrangements. Engineering can use this information to evaluate starter selection and section layout.

Also capture feeder and branch-circuit details, existing bucket or unit sizes, control voltage, and the condition of field wiring that the project intends to retain. Mark each motor as essential, standby, intermittent, or subject to a specific process sequence. Where records are incomplete, identify the uncertainty rather than assuming a rating. Photographs and updated one-line diagrams can help resolve questions before equipment scope and pricing are finalized.

Define control interfaces before ordering

List every connection between the MCC and plant control system, including hardwired start and stop commands, run status, fault indication, permissives, interlocks, and local or remote selection. For networked control, specify the protocol and the intended division of responsibility between the starter equipment and plant controls. Clarify whether existing PLC logic, field devices, and control cables are expected to remain, be modified, or be replaced by others.

Interface schedules should identify terminal conventions, signal types, control power expectations, and required separation between power and control wiring. Note any sequence that must be preserved during a phase transition, such as equipment that cannot restart until a downstream process is ready. These details help prevent assumptions about points, logic, or communications from becoming late design changes. Final interface design should be checked by the responsible controls and electrical engineers.

Coordinate outage scope and handoff

Tie each equipment phase to a plant-approved shutdown window, but distinguish manufacturing and delivery milestones from field installation and commissioning dates. The project team should define who isolates existing equipment, removes it, makes cable terminations, tests circuits, and authorizes energization. Only qualified personnel working under applicable site procedures should perform installation, testing, or switching.

Prepare a phase handoff package with approved drawings, equipment schedules, interface lists, shipping configuration, and open-item status. Confirm what must be verified before release for fabrication, including dimensions, connection locations, and control requirements. For a staged project, identify how each delivery will be labeled and matched to its installation area. This gives purchasing, construction, operations, and controls teams a common basis for managing scope.

Make procurement decisions with the plant in view

Compare proposals against the required motor and control functions, not only the number of starter units. Review lineup arrangement, enclosure requirements, incoming and outgoing connections, control provisions, and the treatment of spare or future spaces. Ask which American-made components are proposed and which details remain subject to confirmation. UL 891 applies to switchboard assemblies; it should not be treated as a blanket certification for MCC or other switchgear equipment.

For a quote, provide the motor and starter schedule, available one-line and layout drawings, control interface requirements, phase quantities, and target outage windows. Include site access limits, preferred shipping sequence, and Georgia delivery location details that affect receiving or staging. We can build new equipment to the defined scope and coordinate shipment requirements, while exact configuration, component availability, and schedule are confirmed for the order.

Planning reference

Project specifications

Specifications are confirmed for each order
ScopeRequested by quote
VoltageBased on project requirements
CurrentSpecified to order
ListingDependent on the applicable assembly. UL 891 applies to applicable low-voltage switchboard assemblies, not medium- or high-voltage equipment.