Set priorities around process consequences
Start by grouping loads according to what happens when power is removed, not simply by motor size or panel location. A control system, essential instrument supply, lubrication pump or ventilation function may be necessary to keep a larger process in a controlled state. Other loads may tolerate interruption or delayed restart. The process and electrical teams should document those dependencies before assigning shed tiers.
For each load or group, identify the operational consequence of interruption, the minimum power needed to maintain a safe state, and any conditions that prohibit automatic restart. Process safety requirements, equipment manufacturer guidance and facility procedures should govern these decisions. Switchgear can execute an approved sequence; it cannot determine which process conditions are acceptable.
Match shedding steps to backup limits
The available generator or other backup source has practical limits beyond its nameplate capacity. Engineers should evaluate connected demand, expected operating combinations, motor starting and other transient loads, and the effect of load changes on the source. A shedding scheme may use measured demand, source status, frequency or voltage conditions, or discrete signals from a supervisory control system. The project design determines which inputs are appropriate and how they are supervised.
Define each shedding stage with a clear trigger, load group, expected response and reset condition. Decide whether the scheme should shed a fixed block, respond to measured conditions, or combine both approaches. Consider what happens if a signal is missing, a breaker does not operate, or the backup source is unavailable. Those failure responses require engineering review rather than assumptions in a switchgear quote.
Specify the assembly and interfaces
For a custom-built switchboard assembly, useful specification inputs include the one-line diagram, system voltage and phase, bus requirements, available fault-current information, feeder quantities, breaker arrangements and the intended source configuration. Identify which feeders are candidates for shedding and which must remain energized. UL 891 applies to switchboard assemblies; it should not be treated as a blanket listing for medium- or high-voltage switchgear or as approval of the complete control strategy.
Describe how the load-shed logic will communicate with the equipment. Clarify whether controls are part of the switchboard scope or provided by another contractor, what terminal points and status indications are required, and who supplies programming and testing. Define any required interlocks, local or remote operation, alarms, metering, and communications interfaces. Confirm division of responsibility early so the equipment design and control-system documents agree.
Protect process safety and recovery
Shedding is only one part of an outage response. Identify loads that support orderly shutdown, hazardous-area controls, fire protection, environmental controls or other facility-defined safeguards, and have qualified process and electrical personnel determine their treatment. Include permissives that prevent an inappropriate restart, and decide which loads require manual authorization before restoration. The design should reflect the facility’s hazard analysis and operating procedures.
Restoration can create a second demand peak if multiple motors or process sections return together. Specify whether loads should reconnect in stages, what delays or operator actions apply, and how the sequence responds to another source disturbance. Testing plans should verify inputs, outputs, breaker operation, alarms and recovery logic under an approved procedure. Commissioning responsibility and any required simulation or witnessed testing should be assigned before procurement.
Make procurement and handoff specific
For a Georgia project quote, share the latest one-line, load list, priority tiers, backup-source details, control narrative, interface requirements and target project milestones. Note known constraints such as available footprint, cable entry, access for installation, environmental conditions and coordination with existing equipment. If documents are preliminary, identify what remains open rather than treating estimates as final ratings or scope.
State the delivery destination in Georgia and the required receiving or jobsite coordination. Nationwide shipping is available, while exact configuration, component availability and schedule are confirmed for each order. Before release, align the approved drawings, breaker and control schedules, terminal plans, and responsibility matrix among the facility, engineer, contractor and control-system provider. This handoff gives the project team a defined basis for installation and functional testing.
Turn the priority plan into a build basis
A useful next step is to mark each candidate load as retain, shed, or conditional, then record its operating consequence, trigger, restart rule and responsible reviewer. Have process safety and electrical engineering teams resolve conflicts and approve the sequence before it becomes a procurement requirement. Submit that approved basis with the switchboard inputs and project schedule so the manufacturer can confirm the proposed equipment scope, interfaces and delivery plan for the Georgia installation.