New electrical distribution equipment, built around your projectServing Georgia
Row of gray electrical control cabinets with switches and indicator lights.

Protection

Breaker Failure Protection

When a circuit breaker receives a trip command but current continues, breaker failure protection can initiate a wider trip to clear the fault. For Georgia engineers, contractors, and facility teams, specifying this function means defining how failure is detected, which upstream devices operate, and how the scheme fits the switchgear and protection system.

Made in USAUL 891 switchboard assemblies — low voltage onlyAccelerated lead times — confirm availability
Project-specific

Define the application and requirements.

Built in the USA

Discuss equipment and assembly options.

Schedule-aware

Confirm lead times for your order.

What the scheme detects

A breaker failure scheme supervises a trip operation and determines whether the breaker interrupted current within the configured interval. Depending on the protection design, it may use current elements, breaker auxiliary contacts, or a combination of signals. If the expected opening is not confirmed, a timer can start a backup trip sequence. The purpose is to limit the time a fault remains energized when the primary breaker does not clear it.

The scheme does not replace primary overcurrent or differential protection. Those functions detect the fault and issue the initial trip; breaker failure logic responds to an unsuccessful clearing operation. Engineers must define which trip sources initiate the logic, how current supervision is applied, and whether a retrip is required before backup tripping. These choices depend on the one-line diagram, fault studies, breaker characteristics, and protection philosophy.

Define the upstream trip path

The backup action may trip an upstream breaker, a bus-tie breaker, or multiple devices needed to isolate the failed breaker and faulted zone. The selected path must be explicit on the protection drawings, including required output contacts, trip coils, interlocks, and any breaker-failure transfer or lockout function. A broad trip can interrupt more load than the primary operation, so the isolation boundary should reflect the consequences of losing each source or bus section.

Coordination is central to the timing decision. The breaker-failure delay must allow the primary breaker time to open and interrupt current, while avoiding an unnecessarily long fault-clearing interval. Engineers should evaluate relay operating time, breaker interrupting time, current decay, communications or interposing device delays, and upstream clearing time. A setting cannot be selected responsibly from a generic value; it requires study against the actual system and equipment data.

Specify the equipment interface

For a new switchgear or switchboard project, identify where the breaker-failure logic will reside and what signals must cross equipment boundaries. The design may involve protective relays, control wiring, terminal blocks, trip circuit supervision, auxiliary contacts, and status indications. Confirm whether the manufacturer is furnishing the logic and wiring, integrating customer-specified devices, or building to issued-for-construction drawings. Clarify ownership of settings, programming, testing, and final protection approval.

Provide the equipment lineup and one-line diagram, breaker and relay data, control schematics, nominal control voltage, available trip circuits, and the intended upstream devices. Include current-transformer locations and ratios, fault-study assumptions, communications requirements, and any existing relay or SCADA interfaces. If the design is not final, identify open decisions rather than treating assumptions as approved. This information helps establish scope and exposes interface gaps before fabrication.

Plan for failure modes and testing

The logic should account for more than a normal trip that fails. Review how the scheme behaves for low-current faults, a stuck auxiliary contact, loss of control power, a failed trip coil, or a breaker that opens mechanically but continues to conduct. The selected current threshold and contact logic affect whether the scheme detects these conditions and whether it could operate when no breaker failure exists. Engineering review should also consider redundant trip paths and the consequences of relay or wiring faults.

A commissioning plan should prove the complete sequence, not just relay output operation. Test personnel can verify trip initiation, timing, retrip if specified, upstream trip outputs, lockout behavior, alarms, and reset requirements using approved procedures and suitable test equipment. Define test points and responsibilities among the switchgear supplier, protection engineer, contractor, and owner. Testing and energization must be performed by qualified personnel under the project’s approved procedures.

Coordinate procurement and delivery

Breaker-failure requirements can affect relay selection, control-circuit design, panel space, wiring, and factory documentation. Include the function in the procurement specification and the drawing review schedule, rather than adding it after the lineup design is settled. For UL 891 switchboard assemblies, confirm the applicable assembly scope separately; UL 891 is a switchboard standard and does not establish a blanket listing for medium- or high-voltage switchgear.

For a Georgia project, share the delivery location, receiving constraints, required arrival window, unloading arrangements, and any sequencing needs for the lineup. Nationwide shipment can be coordinated around the project schedule, but equipment scope, availability, and timing are confirmed for each order. Ask for a quote with the one-line, breaker-failure sequence, equipment ratings and configuration, control requirements, drawing milestones, and requested delivery date. Close the handoff by assigning an engineer to approve logic, settings, and trip boundaries before release.

Planning reference

Project specifications

Specifications are confirmed for each order
ScopeRequested by quote
VoltageBased on project requirements
CurrentSpecified to order
ListingDependent on the applicable assembly. UL 891 applies to applicable low-voltage switchboard assemblies, not medium- or high-voltage equipment.
Request a Quote