Start with the metering responsibility
First establish whether the utility, the facility, or another party supplies and maintains each metering component. The answer affects compartment boundaries, access provisions, wiring responsibility and the information that must be approved before the switchboard layout is released. Do not assume that a standard utility practice applies across Georgia; requirements can vary by serving utility, service arrangement and project.
Ask the utility for its current service and metering requirements, including any preferred drawings or approval steps. Confirm whether the utility requires a dedicated compartment, specified seals or barriers, particular meter access, or a designated location for instrument transformers. Share those requirements with the switchgear manufacturer and project engineer so the proposal can reflect the actual service conditions rather than an unverified assumption.
Define what the section must contain
Describe the metering scope in functional terms: revenue metering, customer monitoring, or both; the number of meters; the circuits or sources being measured; and whether the section is associated with a main, tie, or feeder arrangement. Identify the expected current and voltage sensing approach only from approved project information. The engineer and utility determine suitable instrument transformer ratios, accuracy requirements, burden, polarity and connection details for the application.
Also clarify which components are furnished by the utility and which are included in the manufacturer’s scope. A utility-furnished meter does not necessarily mean the utility furnishes current transformers, potential transformers, terminal blocks, test switches or wiring. A written responsibility schedule prevents gaps between switchboard fabrication, utility work and field installation, and gives purchasing teams a clearer basis for comparing proposals.
Reserve space and preserve access
Metering equipment competes for enclosure space with bus, barriers, wiring ducts and other functional sections. The layout must account for component dimensions, cable routing, bending space, separation requirements and the means of access specified for the assembly. If the utility requires a dedicated, sealable area, that requirement can constrain doors, compartment divisions and the location of adjacent devices. The final arrangement depends on approved drawings and the selected equipment configuration.
Plan access around the people who will read, test or maintain the equipment, while respecting ownership boundaries and site procedures. Review door swing, working space, meter visibility, test access and the route for incoming and outgoing conductors. Do not treat a drawing’s apparent clearance as confirmation of installation acceptability; the project engineer and authority having jurisdiction review the installation against applicable requirements.
Coordinate drawings, signals and labels
Metering affects more than the front elevation. Confirm the one-line diagram, meter schedule, wiring diagrams, terminal arrangement, instrument transformer connections and any required test provisions. For customer monitoring, identify the intended destination of signals and the interface expectations for facility monitoring or control systems. Specify whether communications equipment or field wiring is in scope, and provide protocol or interface details only when established by the project team.
Agree on labels, compartment identification and the drawing approval sequence before release for fabrication. Utility comments may change the compartment arrangement or wiring, so identify who consolidates those comments and who approves revisions. UL 891 applies to switchboard assemblies when the assembly is built and evaluated to that standard; it does not replace utility metering approval, project engineering review or authority review. Confirm the applicable assembly scope for the specific order.
Prepare a complete quotation package
For a useful quote, provide the service voltage and current information, one-line diagram, switchboard lineup dimensions or constraints, metering function, utility standards, meter and instrument-transformer responsibilities, and any preliminary utility comments. Include the required meter location, access and sealing provisions, related control or communications interfaces, and the project schedule milestones. Mark unresolved items plainly so they can be identified as open decisions rather than silently built into the proposed configuration.
For Georgia delivery, share the project location, receiving constraints, unloading plan and required delivery window with the procurement team. Nationwide shipping is available, but routing, packaging and schedule depend on the order and destination; confirm details for the specific project. Before fabrication, coordinate the approved metering drawings among the utility, engineer, contractor and manufacturer, then close out component responsibilities and open technical questions. This handoff helps prevent a completed switchboard from arriving with a metering arrangement that still needs redesign or field clarification.