Start with the functions control power must serve
Control power is distinct from the main power carried by a switchboard or switchgear lineup. Its voltage and source support selected operating and protective functions, which may include circuit-breaker trip and close coils, protective relays, metering, alarms, and communication devices. The actual loads depend on the equipment and control scheme; a device being mounted in the lineup does not by itself establish its control-power requirements.
Document what must operate when normal power is unavailable, what may stop, and whether functions must continue through a loss of the source being monitored. Identify the control voltage required by each device, the expected simultaneous loads, and any brief inrush or momentary demand. These details give the design team a basis for assessing source capacity and distribution instead of assuming that one supply arrangement fits every lineup.
Transformer-fed control power
A control power transformer derives a lower control voltage from an available AC source. This can be a straightforward choice when the intended functions need power only while the selected source is energized and when that source is suitable for the control scheme. The transformer, primary protection, secondary protection, grounding approach, and connections must be coordinated with the equipment design and applicable project requirements.
Ask which circuit supplies the transformer and what happens if that circuit is opened, loses voltage, or is isolated for maintenance. A transformer connected to a source that disappears during a disturbance will not provide continued control power after that source is lost. Specify the primary and secondary voltages, connected loads, protection and isolation expectations, and whether control power is required in particular switching or maintenance states.
Battery-backed arrangements
A battery-backed source can maintain designated DC control functions when its normal charging or AC supply is interrupted. Depending on the engineered scheme, this may support protective relays, breaker trip circuits, alarms, or communications for a defined period. Battery backup does not automatically keep every lineup function available: loads must be assigned to the backed-up supply, and the battery, charger, distribution, and connected devices must be compatible.
Battery selection depends on the required voltage, load profile, duty sequence, and required duration. Clarify whether the design must support a trip operation, repeated operations, alarms, communications, or another specified sequence before control power is restored. The project team must also address battery location, environmental conditions, maintenance access, charging source, monitoring, and replacement provisions. These decisions affect the scope and should be settled before equipment details are finalized.
Understand the consequences of losing control power
When control power is lost, the primary circuit does not necessarily become de-energized, and a breaker does not necessarily open. Depending on the design and state of the equipment, relays may lose power, alarms or indications may be unavailable, and remote trip or close commands may not operate. The outcome depends on the specific circuit, breaker mechanism, protective scheme, and source of the fault; do not infer system behavior from the presence of a transformer or battery alone.
Have the engineer document the expected response to loss and restoration of each control source. Consider whether local operation remains possible, which protective functions remain active, how an operator recognizes the loss, and whether restoration could produce an unexpected command or status change. Review those sequences with the protection and controls design, and confirm operating procedures through the responsible engineering and facility teams.
Questions to settle before requesting a quote
Provide the one-line diagram, control schematics if available, system and control voltages, breaker and relay requirements, and a list of loads that require backup. State the desired source arrangement, required backup duration or duty sequence, alarm and communication needs, and any project standards or specified components. If details remain open, identify them as design decisions rather than treating assumptions as final requirements.
Also share the lineup configuration, incoming and feeder arrangements, available source connections, indoor or outdoor installation conditions, and project schedule. For a Georgia project, provide the ship-to location, site access constraints, delivery window, and coordination needs with installation or construction sequencing. We manufacture new switchgear and switchboard assemblies in the United States using American-made components where specified; configuration, component availability, and delivery timing are confirmed for each order.
Coordinate the handoff and verify the final design
Before release, align the approved control-power scheme with drawings, device schedules, terminal plans, and the project’s protection and operating requirements. Confirm which circuits are AC or DC, which loads are battery-backed, how sources are isolated and protected, and what indications identify loss of supply. Changes to relays, breaker accessories, or communication equipment can alter loads and should prompt a review of the source design.
For a UL 891 switchboard assembly, that standard applies to the switchboard assembly; it does not establish a blanket listing for medium- or high-voltage switchgear. The responsible engineer and authority having jurisdiction must review the complete design and its application. Before requesting pricing, send the available diagrams and explicitly state what must remain operable during a control-power interruption so the proposed configuration can be defined and confirmed.