Start with the load and the correction objective
Define the electrical problem before choosing a bank size. Gather interval demand data where available, utility billing information, existing power-factor readings, load schedules, and operating patterns. Identify which loads run continuously, which cycle, and which may be added later. A single power-factor value from one operating condition may not represent the facility’s needs across shifts or seasons.
Clarify the target and constraints with the project engineer and utility, including whether correction is intended at the service, a major distribution point, or individual loads. Confirm system voltage, frequency, transformer configuration, available fault-current information, and grounding arrangement. These inputs help establish a practical specification without assuming that a particular kvar rating or connection suits every Georgia facility.
Choose placement to match the distribution system
A central bank connected near the main distribution equipment can serve a range of loads and simplify coordinated control. It may also leave upstream transformers and conductors carrying reactive current from downstream loads. Local correction near a large motor or process load can reduce current on the associated feeder, but it adds equipment locations and requires careful coordination with the load’s switching and operating sequence.
Evaluate the physical and electrical point of connection, including bus arrangement, feeder capacity, available space, ventilation, access, and maintenance isolation. If the bank is to be integrated with a new switchboard assembly, define its sections, connections, control wiring, metering interfaces, and protection requirements during design. UL 891 applies to switchboard assemblies; it is not a blanket listing for medium- or high-voltage switchgear.
Specify control for changing loads
For loads that vary, a staged bank with automatic power-factor control may add or remove capacitor steps as conditions change. Specify the measurement point, control target, step sizes, switching method, and operating limits. Ask how the controller responds to light-load conditions, reverse power flow if applicable, loss of sensing, and abnormal voltage. These details affect both performance and how the assembly interfaces with the facility’s controls.
Fixed correction may suit a steady load, but a bank left connected when that load is off can produce overcorrection. Review switching frequency, duty cycle, inrush, and whether contactors or other switching devices are appropriate for the application. The project engineer should determine control behavior and protection settings from the actual system study; equipment selections should not substitute for that review.
Check harmonics and resonance before selecting capacitors
Capacitors interact with system inductance. Depending on transformer and feeder characteristics, adding capacitance can create a resonant condition near harmonic frequencies and amplify voltage or current distortion. Variable-frequency drives, rectifiers, UPS systems, welders, and other nonlinear loads are reasons to examine harmonic conditions rather than assume a standard bank will be suitable.
Share existing harmonic measurements, nonlinear-load details, transformer data, and any prior power-quality studies with the engineer. The review may lead to a plain capacitor bank, a detuned arrangement with series reactors, or another engineered approach. Do not select a reactor or assume a resonance frequency from a rule of thumb alone; the system configuration and operating cases govern the analysis.
Coordinate protection, switching, and equipment interfaces
The specification should address capacitor-duty switching, branch overcurrent protection, discharge provisions, grounding, enclosure conditions, and isolation for inspection. Confirm how the bank’s switching transients and fault contribution affect upstream devices and coordination studies. Protection choices depend on the design, applicable requirements, and engineering review; no configuration should be treated as compliant without review by the responsible engineer and authority having jurisdiction.
For a manufacturer quote, provide one-line diagrams, load and utility data, proposed connection point, voltage and bus information, desired kvar range, control preferences, harmonic study results, and site constraints. Identify whether the request is for a standalone bank or integration with a new switchboard, and include required metering or communications interfaces. Scope, component availability, and schedule are confirmed for each order.
Plan the handoff and Georgia delivery
Before release, align the approved drawings, equipment layout, terminal and cable details, control sequence, protection assumptions, and responsibility for field connections. Resolve who supplies external sensors, control wiring, and any upstream modifications. A clear handoff lets the installing contractor and commissioning team verify the intended operating logic against the final engineered design without relying on assumptions made during procurement.
For a Georgia project, provide the destination, receiving access, requested delivery window, and any site or jobsite handling constraints when the equipment scope is quoted. We build new switchgear and switchboard configurations in the United States and ship nationwide; delivery timing and exact scope are confirmed for each order. Share the one-line diagram, load profile, and harmonic information first so the capacitor-bank placement and control can be evaluated as part of the complete distribution system.