Define the operating cases first
Start with a clear sequence of how the site is expected to operate. Will the generator normally run in parallel with the utility, serve selected loads during an outage, or operate as the primary source while the utility connection is open? Identify startup, shutdown, maintenance, transition and recovery conditions as well as normal operation. Each case can change the required bus arrangement, switching devices, controls and protective coordination.
Document the intended power flow for each mode, including whether the generator may export, whether export is blocked, and what happens when generation exceeds site demand. CHP output and facility load may vary independently, so a design based only on peak generator output can miss important operating states. Share expected minimum and maximum generation, load ranges, major motor starts and any planned future capacity changes with the project engineer and switchgear supplier.
Coordinate the utility interconnection
The point of common coupling is a defining project boundary. Confirm its location, the utility service configuration, available fault-current information, metering requirements and the utility’s interconnection criteria. These details inform equipment interrupting and withstand requirements, device arrangement, sensing and control interfaces. The utility’s requirements and the authority having jurisdiction must be reviewed for the specific project; they cannot be inferred from a general CHP application description.
Clarify who provides and configures interconnection relays, communications, metering and trip circuits. Identify signals exchanged among the utility interface, generator controls and switchgear, including breaker status, trip commands and permissives. Where a utility requires a visible isolation point or particular operating sequence, show that requirement on the one-line and control documents early. Confirm responsibilities among the electrical engineer, utility, generator package supplier, controls integrator and switchgear manufacturer before drawings are released.
Design for load sharing and island operation
When the generator operates in parallel with the utility, determine how active and reactive power are controlled and how the system responds to load changes. Multiple generators may require coordinated load sharing, while a single CHP unit may need limits on ramping or export. Specify which equipment performs synchronization and what permissives must be satisfied before closing a generator or tie breaker. The generator controls and switchgear controls should have explicit interface points and agreed operating sequences.
Island operation requires a deliberate separation between the facility’s islanded bus and the utility source, followed by a stable supply for the loads intended to remain energized. Identify the loads that must be shed, the order and thresholds for shedding, and how loads are restored after generation stabilizes. Consider generator capacity during large motor starts and step changes in demand. Automatic transfer, open-transition or closed-transition behavior should be defined rather than assumed, including how the system prevents an unintended connection to an isolated utility circuit.
Match protection to the system study
Protection must address faults and abnormal conditions in both utility-connected and islanded modes. The available fault current, direction of power flow and contribution from generators can differ between modes, affecting relay settings and coordination. The engineering study should establish required protective functions, device ratings, grounding approach and selective tripping objectives. Settings, relay logic and trip paths require qualified engineering review and coordination with the utility and other project stakeholders.
For procurement, provide the latest one-line diagram, short-circuit and coordination study data when available, generator and transformer information, grounding details, and any required relay or control specifications. Identify breaker types, bus ratings, compartment and cable-entry needs, control power, communications and space constraints. UL 891 applies to switchboard assemblies within its scope; it is not a blanket listing for medium- or high-voltage switchgear. Confirm the required equipment type, ratings and documentation for each part of the distribution system.
Build a clear procurement and handoff
A complete quote request should state the service voltage and configuration, source and tie arrangement, generator count and ratings, operating modes, intended load-shedding scheme, utility requirements, and project drawing status. Include the planned installation location, access or footprint limits, cable approach, schedule milestones and delivery destination in Georgia. These details help establish a practical equipment scope and identify open engineering questions before fabrication. Configuration, component availability and timeline are confirmed for each order.
New switchgear can be custom-built around the documented project requirements, with American-made components where specified and nationwide shipping available. Before release, align approved drawings, device schedules, control narratives, terminal and communication interfaces, and responsibility for settings and field testing. For Georgia delivery, coordinate the ship-to site, receiving access and required delivery window with the project schedule; exact shipping arrangements and timing depend on the order. Assemble the current one-line, utility criteria, generator data and operating sequence into the quote package so the team can resolve CHP interconnection and islanding decisions efficiently.